Building for the Future: Measure A
An investment in students, schools, and our community
We are dedicated to providing safe, innovative, and supportive learning environments for all students. By working together, we can ensure that every student has the resources and surroundings they need to succeed.
Phase 1 Projects
Here are a few projects included in phase 1 of the bond:
Playground Replacement
Georgetown, Northside and Otter Creek Schools received new playgrounds to ensure student safety, accessibility, and long-term facility sustainability.
Golden Sierra Track & Field
Upgrading the synthetic turf and installing a 6 lane all-weather track provides year round access for our students and community.
HVAC Installation
Installing modern heating and air conditioning provides for year-round comfort and usability of the MP rooms at Georgetown and Northside Schools.
Golden Sierra Track & Field Project: Measure A Progress Update 8/28/2026
We are excited to share an update on the Measure A bond-funded facility improvements underway at Golden Sierra High School! Construction is moving along on state-of-the-art upgrades designed for our students, student-athletes, and our Divide community.
Key Project Upgrades & Features
- Synthetic Turf & Multi-Sport Lines: Turf installation is scheduled to begin on Monday, August 31, with green on the field expected by mid-September. The new synthetic surface replaces traditional SBR black rubber granules with an eco-friendly infill mixture of sand and ceramic cooling performance granules, keeping the field cooler on hot days while meeting strict safety and performance guidelines. Underneath, a new shock-absorbing performance and safety pad, guaranteed for 20 years, ensures athlete comfort and long-term durability capable of lasting through three turf lifecycles. The turf itself includes a 10 year warranty, as well as dedicated line markings to accommodate both football and soccer!
- All-Weather Track & Field Events: A modern 6 lane winterized track engineered for year-round training, events, and competition regardless of weather conditions. The facility features dedicated event spaces with upgraded track & field areas, including discus and javelin spaces integrated directly into the field end zones.
- Accessibility & Campus Experience: Dedicated ADA compliant parking, a new ticket booth, and expanded accessible seating and pathways to ensure a smooth, inclusive game-day experience for all fans.
- Infrastructure Improvements: A comprehensive drainage system replacement and asphalt prep work to protect long-term site quality and safety.
- Sound System Upgrades & Relocation: Existing speakers will be relocated to enhance the event experience for all spectators. The setup will also feature additional speakers inside the stadium and within our announcer’s box to ensure optimal audio coverage.
Current Timeline & Safety Notice
Although we did not anticipate a full drainage replacement, site testing required incorporating a full drainage replacement into the project scope. This necessary replacement has delayed the installation of the turf and track surfacing by approximately 15 days. We know how important Homecoming is to our students and community. We are currently working on a temporary access plan to allow us to play our two scheduled home games in October during construction. Priority will be given to the Homecoming game on October 2nd. Further updates will be provided on our website and through ParentSquare as information is made available from our construction team.
Looking Ahead
We sincerely appreciate your patience and understanding while our stadium is under construction. We know the temporary disruption to our usual activities and access is an inconvenience, but we are thrilled for what lies ahead. Once complete, these transformational upgrades will provide a safer, top-tier home for Grizzly athletics, while giving valued community partners, like Gold Nugget Soccer, Junior Grizzy Football, and our community a site to host events for years to come, and serve as a source of pride for the entire Black Oak Mine community.
Thank you to our community for your continued support in making these transformational upgrades possible!
Frequently Asked Questions
Have additional questions? Contact us and we’ll be happy to help!
-
Bond funds are dedicated to long-term facility improvements and cannot be used for salaries or daily operating expenses.
-
Measure A‘s estimated average annual tax rate is less than $40 per $100,000 of assessed valuation for 15 years. Assessed valuation should not be confused with market value. The assessed valuation is the value placed on property by El Dorado County and is typically lower than market value.
-
Updates will be shared through district communications and public reports.
-
District leaders, staff, and community members worked together to evaluate the current state of district facilities, examine existing challenges, analyze future enrollment projections, and assess long-term facility needs.
-
An Independent Citizens' Oversight Committee (COC), made up of local community members, business leaders, and taxpayer representatives, is established to monitor bond expenditures, review annual audits, and ensure funds are spent strictly according to voter-approved projects. The committee meets several times a year. These meetings are posted on the District website and are open to the public.
-
You can contact Carrie Arnett, superintendent at carnett@bomusd.org or phone the district office at 530-333-8300.
Building Tomorrow, Together
This bond represents a shared investment in our students and our community’s future. Follow us on social media and download the ParentSquare App to receive important updates and stay informed on the latest projects happening in our district.